Main Contractor - Skanska Construction
Development - Shell and Core Office Development
M&E Contractor - Skanska Rashleigh Weatherfoil
RMS Contract Value - £1,750,000
Contract Period – Nov 08 to Nov 2009
RMS Contract Works – Full Public Health and Mechanical Shell and Core Installation over 14 floors. Due to an incredibly short programme large sections of plant and pipework, were pre-fabricated off site in purpose built frames to maximise speed of installation on site. The Public Health installation included all Domestic Water Services and Drainage pipework. Many adaptions were required to combine the extensive suspended drainage in the three basements to discharge into three large interceptors.